3 Verified Outcomes
Twin-kiln exhaust deemed too challenging to recover. £84,000/yr fuel reduction; dryer gas eliminated; grant secured.
Engineering Journey

Challenge

Twin-kiln operation prevented conventional heat recovery approaches.

Solution

Process integration study and bespoke automated heat recovery strategy.

Results

  • Reduced natural gas consumption
  • Improved process efficiency
  • Enhanced asset life

Commercial Impact

£84,000/yr fuel cost reduction; government funding secured